Statistics and Chronology of the Royal Albert Bridge


Major Dimensions


Length of each Main Span (Two)

Overall length of each Main Truss

Distance between chain eye attachments

Height of tube centre above roadway

Height of roadway above HWOST

Devon Approach Spans (East/West)

 

 

 

 

Cornwall Approach Spans (East/West)

 

 

 

 

 

Total Overall length of Bridge

 

CHRONOLOGY

 

Cornwall Railway Act of Parliament

Contract with C. J. Mare

Launch of Great Cylinder

Great Cylinder finally positioned

C.J. Mare Bankruptcy

Testing of Cornwall Span

Floating of Cornwall Span

Start of Cornwall Span lifting

Cornwall Span in position

Floating of Devon Span

Start of Devon Span lifting

Devon Span in position

Testing of Bridge

Opening Date

 

MATERIALS USED IN CONSTRUCTION

  

Wrought Iron

Cast Iron

Masonry & Brickwork

Timber


455ft

 461ft

450ft

72ft

100ft

3 @ 69ft 6in

1 @ 72ft 6in

1 @ 78ft 0in

1 @ 83ft 6in

1 @ 93ft 0in

1 @ 93ft 0in

1 @ 83ft 6in

1 @ 78ft 0in

1 @ 72ft 6in

5 @ 69ft 6in

I @ 67ft 6in

2,187ft 6in

3 August 1846

January 1853

May 1854

February 1855

21 September 1855

Summer 1857

1  September 1857

25 November 1857

19 May 1858

10 July 1858

9 August 1858

16 February 1859

20 April! 859

2 May 1859

2,650 tons

1,200 tons

17,000 yards3

14,000ft3